Plaunt Street South Reconstruction Phase 2

Project Description

Renfrew Town Council has awarded the construction of Plaunt Street South Reconstruction Phase 2 project to Bonnechere Excavating Inc. (BEI).  The construction includes storm and sanitary sewer replacement, watermain replacement and road reconstruction including sidewalk, curbs, landscaping, new water and sanitary services to the property line. 

The project will be separated into two parts as the construction award was later than excepted due to a late funding announcement.

Segment 1 (2017)

Limits:          Plaunt Street South from Railway Avenue to Munroe Avenue East and  

         Munroe Avenue East from Plaunt Street northerly to ravine.

        Construction: Week of September 5th, 2017 and will continue until late Fall 2017 .

Segment 2 (2018)

Limits:            Plaunt Street North from Munroe Avenue East towards the end of the cul-de-sac
Construction: Spring 2018

Road Closures

Week of September 18th

Week of September 25th until further notice

Week of October 2nd until further notice

Notices